Google has suspended work on an artificial intelligence data center in Belgium after regional officials in Wallonia said the company lacked the required planning permission. The U.S. technology group confirmed the stoppage at the site in Farciennes, a former mining area near Charleroi, saying it acted “consistent with the direction from local authorities and pending additional guidance.”
Wallonia government spokesman Nicolas Yernaux described the work as “a major offence — the illegal construction of a building covering three hectares” on a 50-hectare parcel. In its own statement, Google said it has operated in Belgium for more than 15 years and “remain[s] committed to complying with local laws.”
The dispute has been building for months. Google applied to revise the terms of its permit so the facility could use a cooling system drawing water from the nearby River Sambre, replacing the air cooling envisioned in the original plan. Regional officials rejected that request over the summer, but construction carried on, drawing objections from environmental groups.
“That Google continues to build without a permit is disrespectful to the environment, local residents, and the law,” said Joeri Thijs of Greenpeace Belgium, who added that “the construction of energy-guzzling data centers cannot remain under the radar” as climate pressures mount.
Google has challenged the permit refusal in court, with a hearing set for January.
The standoff reflects widening friction over the infrastructure underpinning the AI boom. Data centers are energy-intensive, and opposition to new projects has intensified as developers race to secure land, power and water.
Note: Figures from Data Center Map, which tracks operational and pre-operational sites.
In the U.S., the spread of data centers became a campaign issue during the midterm elections, with three states electing Democratic senators and governors who backed tighter regulation of the facilities.
For Google, the Belgian case adds to a growing list of European legal and regulatory entanglements as it and rival hyperscalers expand capacity to serve AI workloads. A prolonged halt at Farciennes could delay the company’s regional compute build-out and raise the cost of compliance reviews for similar projects.
The immediate question is whether the court in January sides with the region or the company. Until then, the site is expected to remain idle.
Once added, BigGo Finance appears first in Google Search Top Stories, so you get the broadest, most up-to-the-minute, and most comprehensive global financial news first.
The news and data on this website are for reference only and do not constitute investment advice or an offer to buy or sell. Information is sourced from exchanges and public sources, and may be delayed, interrupted, or updated. While we strive for accuracy, we do not guarantee timeliness, correctness, or completeness. Content may include external links for which we are not responsible. By using this site, you agree that we and our partners are not liable for any losses. Investment carries full responsibility; please carefully assess risks and consult professionals. If there are errors in the content, please contact us for correction.